Saturday, January 21, 2012

Progress Report

349 Coyote Ridge Drive, Smithfield, Utah 84335
(349 South 1100 East)
January 13th
Roof sheeting complete,
last wood edging above garage being placed

January 19th
Metal strips on roof edge and tar paper are on. Worker is up on the roof shingling. Main bath tub/shower is installed as is most ductwork and 'mechanical' stuff. All but a few of the windows have been put in. We mainly do 'drive-bys' as we are not supposed to be on site while workers are present.


January 21st
The front entry door and man door in garage were installed yesterday. The furnace is in, most of electrical and plumbing are done. We have the typical frustrations of building a home. We are making them change out two windows already. We thought it is a 'no-brainer' to have windows that open in the bathrooms but fixed 'picture' windows were installed. We'd like a couple more electrical outlets and phone and cable jacks put in. The north slope of the roof is the only remaining side without shingles. I think it is a miracle they even got the rest done with the massive amounts of precipitation we've been having.

No comments: